August 3, 2018

The big takeaways this week:

  • This Saturday (August 4th), there will be intermittent closures of southbound Healdsburg Avenue, northbound Vine Street and Mill Street west due to construction work on several of the roundabout median islands ahead of final paving. This work will occur during the day, between 7 a.m. – 5 p.m.
  • This coming Monday and Tuesday (August 6th-7th), between 8 p.m.-6 a.m., we need to close North/South Healdsburg Avenue, East/West Mill Street, and Vine Street to vehicular traffic so the contractor can perform final paving of these roads leading into/out of the roundabout. Please take alternate routes; detour routes will be signed to provide access around the closures.

Now, here’s the rest of the update:

Railroad Construction: A subcontractor installed railroad equipment for future railroad-crossing arms. The crossing arms themselves will be installed when SMART starts to operate in Healdsburg.

Southeast Surface Improvements (S. Healdsburg Ave.)
This week: Placed stone veneer on the decorative stone walls.
Next week: The contractor will perform rock grade surface improvements and form and pour concrete sidewalks. The latter is scheduled to continue into  next week.

Vine St. Surface Improvements
This week and next week: A subcontractor will form and pour concrete sidewalks.

Landscaping: 
This week: A subcontractor is installing irrigation laterals. This work is scheduled through next week.
Next week: A subcontractor will amend the soil – this work is scheduled through the following week.