July 20, 2018

The big takeaways:

  • The contractor has finished installing the median islands leading into and out of the roundabout.
  • Planning for the final pavement overlay of N./S. Healdsburg Ave., E./W. Mill and Vine St. is ongoing. Final paving would most likely be done at night over several evenings.
  • City crews have installed some of the streetlights near and around the circle to light the roundabout.

Southeast Surface Improvements (S. Healdsburg Ave.)
This week: a subcontractor is placing stone veneer on the decorative stone walls. This work will continue through next week.

Next week:
– Workers will prepare the rock-grade surface for construction of the concrete sidewalks.
– Workers will start to form and pour concrete sidewalks. This work will continue through the week of July 30.

Vine St. Surface Improvements
This week: Workers prepare the rock-grade surface for construction of the concrete sidewalks

Next week: Form and pour concrete sidewalks. This work extends into the middle of next week.

Median Islands
This week: Workers finished installing the median islands for North and South Healdsburg Ave.

Landscaping
This week: The subcontractor is installing the irrigation mainline. This work continues into the next week.

Next week: The subcontractor will install irrigation laterals. This work continues through most of the week of July 30.