July 12, 2018

Can you believe summer is already half-over? If you’ve driven the roundabout recently, you’ll see the progress we’ve made as we continue to plow ahead.

The big takeaways you should know about: 

  • The contractor is installing the median islands this week for N./S. Healdsburg Ave., E./W. Mill St., and Vine St. and will finish installation early next week.
  • Looking Ahead: The contractor may perform a final pavement overlay on N./S. Healdsburg Ave., E./W. Mill St., and Vine St. leading into the roundabout during the week of July 23. This work would occur overnight and could take two nights to complete. While this work is being done, these roads will be closed to vehicular access. Note that the week of July 23 is just an estimate; once we finalize the schedule, we will provide a firm date and more details.

Now, on to the rest of the update:

Southwest Surface Improvements (S. Healdsburg Ave.)
This week: A subcontractor is installing a decorative fence near Parish and Elephant in the Room; workers should finish installation early next week.

Northwest Surface Improvements (N. Healdsburg Ave., by Chamber)
This week: A subcontractor is installing decorative stone caps on the walls

Southeast Surface Improvements (S. Healdsburg Ave.)
This week: A subcontractor is installing concrete blocks (CMU) and placing stone veneer on the decorative stone walls. This work will continue through the end of July.
Next week: The contractor will begin rock grade surface improvements. This work should be completed the following week.
Week of July 23: A subcontractor is scheduled to form and pour concrete sidewalks

Vine St. Surface Improvements
Next week:

  • The contractor will improve the rock grade surface to prep for sidewalks to be poured
  • A subcontractor will form and pour concrete paving areas.

Final Pavement Overlay: We’re estimating that the contractor will perform this work over1-2 nights during the week of July 23. We will provide more information once this schedule has been finalized.

Median Islands: The contractor is installing the median islands for E./W. Mill, N./S. Healdsburg Ave., and Vine Street this week and will finish early next week.

Landscaping: A subcontractor is installing irrigation main line and laterals.