June 22, 2018

The big takeaway this week is there will be night road work this Sunday, June 24, through Thursday, June 28. In order to create a smooth road surface, the City contractor will dig up old asphalt and concrete and re-pave sections of road near the roundabout each night –- between 8 p.m. and 6 a.m. — to minimize disruption and inconvenience to Healdsburg residents, workers, and visitors.

This work makes it necessary to close vehicular access to the roundabout between 8 p.m. – 6 a.m., June 24-28, from:

• South Healdsburg Avenue from Exchange Avenue.
• Westside Road/ West Mill from Vineyard Plaza/Carl’s Jr. driveway
• East Mill from Center Street
• North Healdsburg from Matheson
• Vines Street from Vineyard Plaza entrance

Please note that from Monday through Wednesday, June 25-27, the road surface into and through the roundabout will be gravel/compacted rock, so please drive more carefully and slower than usual. Please consider using alternate routes during this time.

Now, on to the rest of the construction update:

Southwest Surface Improvements (S. Healdsburg Ave.)
This week:

  • Placed interlocking pavers
  • Built additional stone wall

East Mill St. Surface Improvements
Next week: Install irrigation system and top soil. This work continues into next week.

Southeast Surface Improvements (S. Healdsburg Ave.)
This week:

  • Form, pour and strip pervious/standard gutter areas
  • Improve rock grade surface

Next week: Install stonewall

Vine St. Surface Improvements
This week:

  • Form, pour and strip pervious/standard gutter areas
  • Improve rock grade surface