June 8, 2018

Construction work continues to progress on the roundabout. Here’s a quick look at the big takeaways coming up in the next week or so:

  • Next Monday night, June 11, starting around 6 p.m. and ending early the following morning, the contractor will demolish the road, curb, gutter, and sidewalk on a portion of Vine Street and West Mill Street, by Exchange Bank.
  • On Tuesday night, June 12, starting around 6 p.m. and ending early the following morning, the contractor will excavate and place structural soil on the same portion of Vine and East Mill.
  • After this night work, during daytime hours, the contractor will sub-grade, rock-grade, and form, pour, and strip curb and gutter areas on Vine Street.
  • Looking Ahead – Paving Plan:¬†We are in the process of creating a plan and schedule to re-pave Healdsburg Avenue south of the circle as well as short portions of Mill, Vine and N. Healdsburg Ave. This work may commence the week of June 25, but we will confirm all dates and timing in a future update.