May 25, 2018

The big takeaway:  The contractor is installing interlocking pavers on Healdsburg Avenue in front of Rockpile to complete the sidewalk on the east side – another step towards providing pedestrian access on this stretch of Healdsburg Ave. Here’s the rest of the update:

Southwest Surface Improvements (S. Healdsburg Ave.)
This week:

  • Place lithocrete – an architectural concrete with embedded recycled materials (for color and decoration). This work continues into next week.
  • Place interlocking pavers in sidewalk area. This work is scheduled through June 8.

Week of June 4: Sub-contractor to install irrigation system

Northwest Surface Improvements (Healdsburg Ave.)
Next week: Sub-contractor to install irrigation system

East Mill St. Surface Improvements
This week: Placed interlocking pavers
Week of June 4: Sub-contractor to install irrigation system

Railroad Construction
This week: Installed CMU and placed stone veneer on wall
Next week: Finish roundabout truck apron

Southeast Surface Improvements (S. Healdsburg Ave.)
This week:

  • Complete demolition of old pavement to prep for the installation of curb, gutter and sidewalk in this area.
  • Sub-graded and rock-graded curb and gutter. This work is scheduled for next week.
  • Excavated for bioretention areas

Next week:

  • Excavate area for bus pad
  • Stake stone wall

Week of June 4:

  • Form and pour bus pad
  • Form, pour and strip pervious and standard curb and gutter areas
  • Form footing and install rebar for stone wall