Construction in and around the roundabout is really coming along nicely. The big takeaways this week:

  • If you’ve driven around it recently, you’ll see that the circle is being constructed as well as decorative stone walls. The stone wall within the circle will be several feet high and tie into the landscaping within the circle.
  • Starting the week of May 7, a subcontractor will place lithocrete, an architectural concrete with embedded recycled materials, on South Healdsburg Avenue. This along with cobbles placed in the center circle will be used to delineate the flow and direction of Foss Creek. This decorative cobble feature is also porous, which will help cut the amount of storm water run-off.

Here are several photos, taken yesterday, of the stone walls in progress as well as of the circle.

Now on to the rest of the roundabout update:

Southwest Surface Improvements (S. Healdsburg Ave)
This week through next week:

  • Form and pour concrete paving areas down to Singletree Café

Week of May 7:

  • Place lithocrete A and B

Northwest Surface Improvements (N. Healdsburg Ave)
This week through next week:

  • Install irrigation system and top soil
  • Place stone veneer on decorative stone walls
  • Install 4-ft. metal fence – this is along Vine Street.

East Mill St. Surface Improvements
Next week:

  • Install irrigation system and top soil
  • Place stone veneer on decorative stone walls
  • Install 4-ft. metal fence – this is along the rail trail

Roundabout construction (within the circle)
This week:

  • Form and pour 36-inch rolled concrete curb and gutter
  • Form and pour 6-inch concrete curb

This week through next week:

  • Grade roundabout truck apron

Next week:

  • Pour truck apron stamped colored concrete paving
  • Excavate for decorative stone wall
  • Form and pour stone wall footing

Week of May 7:

  • Patch-pave the roundabout

Southeast Surface Improvements (S. Healdsburg Ave)
This week:

  • Demolish old pavement, curb and gutter
  • Subgrade and rock-grade curb and gutter

Week of May 7:

  • Form, pour and strip pervious and standard curb and gutter areas